Dear Fulvio,
thanks for your email below..
i can send you our plan so that to know the exact dates that we will send our secondee from CUT to Pagni (GREECE) and AIGIS (Germany).

We have already arranged our secondees so that we will follow the plan below..

Please let me know if you agree.. Until August 2021 we will complete 24PMs out of 48

You can see from the table below the remaining  24PMs with the mark "Pending" 

I hope to accept this schedule and to confirm me if its ok



Name of Secondee 

Hosting 

Continues 

WP 

Tasks 

S 

Duration 

Start Month 

End Month 

Portal Dates 

Completed / Pending 

Deviation 

Kostas Iordanou 

PAGNI (GREECE) 

NO 

2 

2.1 

4 

2 

Mar-2020 

Apr-2020 

 

 

02 March 2020 - 01 March 2021 

 

 

Completed  

Was Feb-2020 - May-2020 

Kostas Iordanou 

PAGNI (GREECE) 

YES 

3 

2.4 

6 

3 

May-2020 

Jul-2020 

Was Feb-2020 - May-2020 

Kostas Iordanou 

PAGNI (GREECE) 

YES 

4 

4.1 

9 

3 

Aug-2020 

Oct-2020 

Was Jul-2021 - Oct-2021 

Kostas Iordanou 

PAGNI (GREECE) 

YES 

2 

4.2 

12 

4 

Nov-2020 

Feb-2021 

Was Dec-2022 - Mar-2023 

Pantelitsa Leonidou 

AEGIS (GERMANY) 

NO 

4 

4.1 

9 

4 

Aug-2020 

Nov-2020 

 

03 August 2020 - 02 August 2021 

 

Almost Completed  

 

Pantelitsa Leonidou 

AEGIS (GERMANY) 

NO 

4 

4.2 

13 

4 

Dec-2020 

Mar-2021 

Was Jun-2022 - Sep-2022 

Pantelitsa Leonidou 

AEGIS (GERMANY) 

YES 

3 

3.2 

17 

4 

Apr-2021 

Jul-2021 

Was Apr 2022 - Jul-2022 

Nikolaos Salamanos 

PAGNI (GREECE) 

NO 

3 

3.2 

27 

9 

Feb-2022 

Oct-2022 

04 February 2022 – 03 November 2022 

Pending 


Nikolaos Salamanos 

AEGIS (GERMANY) 

NO 

3 

3.2 

36 

3 

Nov-2022 

Jan-2023 

04 November 2022 – 03 February 2023 

Pending 


Markos Charalambous 

AEGIS (GERMANY) 

NO 

5 

5.1 

31 

4 

Jun-2022 

Sep-2022 

 

 

13 June 2022 – 12 June 2023 

 

 

Pending 

 


Markos Charalambous 

AEGIS (GERMANY) 

YES 

5 

5.1 

35 

4 

Oct-2022 

Jan-2023 


Markos Charalambous 

AEGIS (GERMANY) 

YES 

3 

3.2 

39 

4 

Feb-2023 

May-2023 

 

Total PMs 

48 

  

  

 

  

 



From: AERAS <aeras-bounces@mailman.di.unimi.it> on behalf of fulvio.frati@unimi.it <fulvio.frati@unimi.it>
Sent: 07 July 2021 11:22
To: aeras@di.unimi.it <aeras@di.unimi.it>
Subject: [AERAS] proposed new secondment plan
 
Dear Partners,

 

we hope this email will find you well and healthy.

 

to prepare the amendment for the extension, we have first to agree on the
new deadlines and a new plan for the secondments.

 

Please find attached our proposal. In particular:

 

*       In the sheet "SecondmentList" you will find the situation as it is
now in the portal (without the extension)
*       In "+12Mo" a proposed secondment plan where we only added 12 months
to the deadlines, taking into consideration the secondments already executed
by CUT that are left unchanged
*       In "STS CY" you can find the state taking into consideration the
conflicts (highlighted in red) we can have upon the change of premises of
STS (from Switzerland to Cyprus)
*       In "Proposed" you can find a solution to solve the conflicts, given
that we can not have secondments from/to the same country and from different
kind of partner (University to University or Company to Company not allowed)
*       In "Deliverables Plan" a proposal new plan for the deliverables,
with a consequent change in WPs duration proposed in the sheet "WPs"

 

Please take a look at it and give us our opinion.

 

Kind regards

Fulvio

 

____________________________________________

SESAR Lab - Computer Science Department

Università degli Studi di Milano

Via Celoria, 18
20133 Milano - ITALY
Tel. +39-02-503 16381
 <http://sesar.di.unimi.it/> http://sesar.di.unimi.it
____________________________________________